Pier Closure Schedule for April 2013

In order to improve public safety and ensure the continued use of the pier, construction upgrades to repair and replace damaged piles and cross-braces will take place from March 18 - May 17, 2013 with intermittent pier closures. Below please find the construction timeline for April 2013.

April 8 - 14:

  • Full time closures during the week with a potential for partial opening after work hours
  • Partial openings during weekend

April 15 - 21:

  • Full time closures during the week with a potential for partial opening after work hours
  • Partial openings during weekend

April 22 - 28:

  • Full time closures during the week with a potential for partial opening after work hours
  • Partial openings during weekend

April 29 -  May 5:

  • Full time closures during the week with a potential for partial opening after work hours
  • No weekend closures

We recognize the inconvenience associated with the pier upgrade and greatly appreciate your patience during this time.